Explore how HPM Consultants brings clarity to complex scheduling,delay and damages disputes.
HPM Consultants was retained to evaluate delays affecting the Bowery Bayside Multi-family Apartment Buildings project, including extended punch-list corrections, work slowdowns, and prolonged completion activities. The dispute focused on determining the causes of significant schedule overruns and whether contractor performance and coordination issues impacted substantial project completion.



HPM Consultants conducted a forensic schedule and as-planned versus as-built analysis to evaluate the impact of construction delays, punch-list activities, and project execution issues on the completion timeline. The review included analysis of contemporaneous schedules, contractor progress, work sequencing, termination-related events, and critical-path activities affecting project completion.
HPM Consultants determined that the project experienced substantial delays driven by extended architect punch-list and correction activities, work slowdowns, and prolonged construction performance beyond the original contract duration. The analysis identified significant schedule impacts across multiple project areas and provided a fact-based evaluation of the delays affecting overall project completion.


Construction disputes often develop when project delays are not identified, tracked, or addressed properly. By the time disagreements reach formal claims or litigation, the underlying issues may have existed for months. This is why schedule analysis plays such an important role in successful project management. A well-maintained schedule does more than track progress. It helps project […]

Project profitability depends on completing work efficiently, managing costs, and meeting schedule expectations. A construction delay can disrupt all three. While delays are often viewed as scheduling issues, their financial impact can be significant. Even a relatively short delay can increase expenses, reduce productivity, and place pressure on project margins. Understanding how delays affect profitability helps […]