City Of Ventura Veterans Housing Project

The Challenge

HPM Consultants was hired to evaluate delays in the City of Ventura Veterans Project and determine the causes of the late completion. The review focused on whether owner-related issues, including switchgear and design delays, impacted the project schedule. The project completion date was extended by about 348 days beyond the original schedule. Questions also arose about whether contractor activities caused concurrent delays or whether the owner-related delays controlled the critical path.

Our Services

HPM Consultants performed a forensic schedule analysis using project schedules, updates, and critical-path reviews. The analysis tracked how major delay events affected the project completion date over time.

The investigation found that the switchgear fabrication delay postponed permanent power installation and became the main driver of delay. Contractor activities that took longer than planned occurred during available float and did not delay overall project completion.

Outcome

HPM Consultants concluded that the switchgear delay was the primary cause of the delayed completion date on the City of Ventura Veterans Project. The analysis also found that no true concurrent contractor delays existed because the switchgear delay controlled the critical path.

NEWS

recent from Our Blog

13 Interrelated Factors HKA found an average of 13 causation factors per project, highlighting how closely connected schedule and cost issues can become. 1. Correct Logic Activities are properly connected, allowing the schedule to flow as planned and reflect the intended sequence of work. 2. Broken Link One incorrect or missing relationship can create a […]

Independent analysis benefits construction disputes across California

When a construction dispute reaches the point of formal claims, the quality of the delay analysis behind it often determines whether the outcome holds up under scrutiny. A delay damages expert witness in San Diego who has no financial stake in the outcome brings a level of objectivity that internal staff, however capable, simply cannot offer. […]