Dolores Huerta Gardens Apartments

The Challenge

HPM Consultants was retained to evaluate delays affecting the Dolores Huerta Gardens Apartment project arising from extended Southern California Edison (SCE) lead times and additional Solar As-Built Approval requirements introduced during construction. The dispute focused on whether these events qualified as excusable delays under the contract and whether the contractor was entitled to additional time-related compensation.

Our Services

HPM Consultants conducted a detailed contract and forensic schedule review using the AIA A102 2017 and AIA A201 2017 contract provisions together with recognized industry delay-analysis methodologies. A prospective Time Impact Analysis (TIA) was performed to evaluate the impact of SCE lead-time delays and Solar As-Built Approval activities on the project’s critical path and completion date.

Outcome

HPM Consultants determined that the SCE lead-time delay impacted project completion by 89 calendar days, while the Solar As-Built Approval requirement added an additional 22 calendar days of delay. The combined excusable delays resulted in a total project impact of 111 calendar days, supporting the contractor’s entitlement to time-related compensation.

NEWS

recent from Our Blog

Strong schedule analysis helps resolve issues before they become disputes. Contact HPM Consultants for expert guidance

Construction disputes often develop when project delays are not identified, tracked, or addressed properly. By the time disagreements reach formal claims or litigation, the underlying issues may have existed for months. This is why schedule analysis plays such an important role in successful project management. A well-maintained schedule does more than track progress. It helps project […]

Understand how schedule disruptions affect project profitability with help from HPM Consultants

Project profitability depends on completing work efficiently, managing costs, and meeting schedule expectations. A construction delay can disrupt all three. While delays are often viewed as scheduling issues, their financial impact can be significant. Even a relatively short delay can increase expenses, reduce productivity, and place pressure on project margins. Understanding how delays affect profitability helps […]