Who owns project time?

Construction

FORMULATION | ANALYSIS | MANAGEMENT

Is it possible to own project time?Project time remains an abstract concept until it is concretized in the form of a construction schedule. This article explains how surplus time or float can be utilized by project participants to their benefit.
Dr Hendrik Prinsloo is an expert witness and specialist in the analysis construction delay claims

Table of Contents

Is it possible to own project time? To answer this important question, we need to begin with the starting point of a project, the agreement between the owner and the contractor. Like many things in life, we tend to over complicate construction contracts. The bare essentials of a construction contract are the following: an owner undertakes to pay a contractor a sum of money to construct a building within a specific period of time. Project time remains an abstract concept until it is concretized in the form of a construction schedule.

Construction schedules allow for additional or surplus time on some activities. This surplus time is commonly referred to as float.

Only when the float or surplus time is exhausted will the activity become critical or in other words delay the completion date of the project.

Who owns the float? This question is often debated because it is seldom addressed in construction contracts. There are 3 possibilities when it comes to the ownership of float:

  • The float belongs to the contractor
  • The float belongs to the owner
  • The float belongs to the party who utilizes it
    first or in other words it belongs to the project

The most obvious solution to the problem of float ownership is to address it in the construction contract. But what if it is not addressed in the construction contract? The Society of Construction Law Delay and Disruption Protocol (2017) provides some guidance in this regard by looking at the wording of the specific clause in the contract establishing the right to an extension of the contract period:

  • If it is stated that additional time will only be granted when an excusable delay (owner’s risk) causes the contractual completion date to be delayed, it implies that the float should first be exhausted before a right to be granted additional time is established. In essence, the float belongs to the party that utilizes it first.
  • Where it is provided for a contractor to claim for additional time whenever an employer-delay will impact the contractor’s planned completion date, it implies that the owner cannot benefit from the float in the event of an employer-delay. It can therefore be interpreted that the float belongs to the contractor.

The AACE Forensic Schedule Analysis Practice Note No 29R-03 opines that float is shared between the owner and the contractor if float is not addressed in the contract conditions. The information in the practice guides was applied to two commonly utilized contracts to ascertain the ownership of the float:

AIA A201 General Condition Of The Contract For Construction

The AIA A201 (2017) makes no direct reference to the float. Clause 8.3 that deals with delays and extensions of time states that“If the contractor is delayed at any time in the commencement or progress of the Work…, and the architect determines, justify delay, then the Contract Time shall be extended…”

The clause is vague in that it does not refer to the contractual completion date (substantial completion) or the contractor’s planned completion date. Without specific reference to these terms, the Society of Construction Law Delay and Disruption Protocol (2017) guideline is not of use to determine who owns the float. The simple statement in the AACE Forensic Schedule Analysis Practice Note No 29R-03 that float is shared between the owner and the contractor if float is not addressed in the contract conditions might be of help here. If this is applied, the float is owned by the project meaning it can be utilized on a first-come-first- serve basis.

This view might be drawn into question if the wording of this clause is carefully considered. No direct link is drawn between the delay and the contractual completion date. One interpretation of the clause may be that the contractor can claim for any delay and not only for a delay to the contractual completion date. To take this line of thought a step further, one can argue that it opens the door for the contractor to claim for additional time for an owner’s delay that impacted a non-critical activity (an activity with float). If the contractor can claim for the additional time for a non- critical activity it may be argued that the float belongs to the contractor.

FIDIC Conditions Of Contract For Construction

Float or the concept of ownership of float is not explicitly addressed in the FIDIC. Clause 8.4 (extension of time for completion) states that: “thecontractorshallbeentitled,subjectto clause 20.1 [contractor’s claims], to an extension of the time for completion if and to the extent that completion for the purposes of clause 10.1 [taking-over of the works and sections], is or will be delayed….”

This clause makes reference to clause 10.1 (taking-over of the works and sections). Clause 10.1 refers to clause 8.2 (time for completion). Unlike the AIA A201 reference is made to the contractual completion date. If industry practice note guidance is applied, this reference to the contractual completion date implies that the float belongs to the project and should first be exhausted before an extension of time can be considered.

Conclusion

Float ownership remains challenging despite the guidance provided by industry practice notes. It is advisable to consider the specific circumstances of a project before a final decision on float ownership is reached. In the current age of fast-paced technological advancements, we can expect that changes during the construction period will remain a predominant cause of delay. Project time can no longer be an afterthought in construction contracts. Issues like float, concurrent delays, and delay analysis deserve a more prominent role within the pages of our construction contracts.