Bowery Bayside Multi-family Apartment Buildings

The Challenge

HPM Consultants was retained to evaluate delays affecting the Bowery Bayside Multi-family Apartment Buildings project, including extended punch-list corrections, work slowdowns, and prolonged completion activities. The dispute focused on determining the causes of significant schedule overruns and whether contractor performance and coordination issues impacted substantial project completion.

Our Services

HPM Consultants conducted a forensic schedule and as-planned versus as-built analysis to evaluate the impact of construction delays, punch-list activities, and project execution issues on the completion timeline. The review included analysis of contemporaneous schedules, contractor progress, work sequencing, termination-related events, and critical-path activities affecting project completion.

Outcome

HPM Consultants determined that the project experienced substantial delays driven by extended architect punch-list and correction activities, work slowdowns, and prolonged construction performance beyond the original contract duration. The analysis identified significant schedule impacts across multiple project areas and provided a fact-based evaluation of the delays affecting overall project completion.

NEWS

recent from Our Blog

Expert credibility matters most once a case proceeds

Choosing the right expert can shape the outcome of a construction dispute long before a case ever reaches trial. Attorneys evaluating a construction expert witness typically look well beyond a resume, weighing technical knowledge, communication skills, and courtroom presence together. Construction scheduling experts in San Diego who check every one of these boxes can make the difference […]

Expert analysis behind construction disputes

Construction projects rarely follow a perfect timeline. Unexpected weather, design changes, labor shortages, material delays, and coordination issues can all affect progress. When these setbacks lead to financial losses, determining who is responsible and how much compensation is owed becomes a complex process. This is where proper evaluation of delay damages plays a critical role. […]