Bowery Bayside Multi-family Apartment Buildings

The Challenge

HPM Consultants was retained to evaluate delays affecting the Bowery Bayside Multi-family Apartment Buildings project, including extended punch-list corrections, work slowdowns, and prolonged completion activities. The dispute focused on determining the causes of significant schedule overruns and whether contractor performance and coordination issues impacted substantial project completion.

Our Services

HPM Consultants conducted a forensic schedule and as-planned versus as-built analysis to evaluate the impact of construction delays, punch-list activities, and project execution issues on the completion timeline. The review included analysis of contemporaneous schedules, contractor progress, work sequencing, termination-related events, and critical-path activities affecting project completion.

Outcome

HPM Consultants determined that the project experienced substantial delays driven by extended architect punch-list and correction activities, work slowdowns, and prolonged construction performance beyond the original contract duration. The analysis identified significant schedule impacts across multiple project areas and provided a fact-based evaluation of the delays affecting overall project completion.

NEWS

recent from Our Blog

Regular schedule reviews help teams record progress, sequencing, and developing constraints while the work is underway.

A schedule update is more than a monthly administrative task. It creates a time-stamped record of how the project is progressing, which activities have moved, and where constraints are developing. When a dispute arises, a construction scheduling expert witness in San Diego may rely heavily on those updates to understand how the critical path changed over […]

Schedule and project records help connect delay events to their effect on completion.

A delay claim becomes easier to evaluate when the schedule story and the cost story can be traced to the same project events. When owners, contractors, or attorneys need a delay damages expert witness in San Diego, the useful starting point is not a damages total. It is a supported timeline showing what happened, which […]