HPM Consultants was retained to evaluate delays affecting the Bowery Bayside Multi-family Apartment Buildings project, including extended punch-list corrections, work slowdowns, and prolonged completion activities. The dispute focused on determining the causes of significant schedule overruns and whether contractor performance and coordination issues impacted substantial project completion.



HPM Consultants conducted a forensic schedule and as-planned versus as-built analysis to evaluate the impact of construction delays, punch-list activities, and project execution issues on the completion timeline. The review included analysis of contemporaneous schedules, contractor progress, work sequencing, termination-related events, and critical-path activities affecting project completion.
HPM Consultants determined that the project experienced substantial delays driven by extended architect punch-list and correction activities, work slowdowns, and prolonged construction performance beyond the original contract duration. The analysis identified significant schedule impacts across multiple project areas and provided a fact-based evaluation of the delays affecting overall project completion.


13 Interrelated Factors HKA found an average of 13 causation factors per project, highlighting how closely connected schedule and cost issues can become. 1. Correct Logic Activities are properly connected, allowing the schedule to flow as planned and reflect the intended sequence of work. 2. Broken Link One incorrect or missing relationship can create a […]

When a construction dispute reaches the point of formal claims, the quality of the delay analysis behind it often determines whether the outcome holds up under scrutiny. A delay damages expert witness in San Diego who has no financial stake in the outcome brings a level of objectivity that internal staff, however capable, simply cannot offer. […]