HPM Consultants was hired to evaluate delays in the City of Ventura Veterans Project and determine the causes of the late completion. The review focused on whether owner-related issues, including switchgear and design delays, impacted the project schedule. The project completion date was extended by about 348 days beyond the original schedule. Questions also arose about whether contractor activities caused concurrent delays or whether the owner-related delays controlled the critical path.



HPM Consultants performed a forensic schedule analysis using project schedules, updates, and critical-path reviews. The analysis tracked how major delay events affected the project completion date over time.
The investigation found that the switchgear fabrication delay postponed permanent power installation and became the main driver of delay. Contractor activities that took longer than planned occurred during available float and did not delay overall project completion.
HPM Consultants concluded that the switchgear delay was the primary cause of the delayed completion date on the City of Ventura Veterans Project. The analysis also found that no true concurrent contractor delays existed because the switchgear delay controlled the critical path.


Choosing the right expert can shape the outcome of a construction dispute long before a case ever reaches trial. Attorneys evaluating a construction expert witness typically look well beyond a resume, weighing technical knowledge, communication skills, and courtroom presence together. Construction scheduling experts in San Diego who check every one of these boxes can make the difference […]

Construction projects rarely follow a perfect timeline. Unexpected weather, design changes, labor shortages, material delays, and coordination issues can all affect progress. When these setbacks lead to financial losses, determining who is responsible and how much compensation is owed becomes a complex process. This is where proper evaluation of delay damages plays a critical role. […]