City Of Ventura Veterans Housing Project

The Challenge

HPM Consultants was hired to evaluate delays in the City of Ventura Veterans Project and determine the causes of the late completion. The review focused on whether owner-related issues, including switchgear and design delays, impacted the project schedule. The project completion date was extended by about 348 days beyond the original schedule. Questions also arose about whether contractor activities caused concurrent delays or whether the owner-related delays controlled the critical path.

Our Services

HPM Consultants performed a forensic schedule analysis using project schedules, updates, and critical-path reviews. The analysis tracked how major delay events affected the project completion date over time.

The investigation found that the switchgear fabrication delay postponed permanent power installation and became the main driver of delay. Contractor activities that took longer than planned occurred during available float and did not delay overall project completion.

Outcome

HPM Consultants concluded that the switchgear delay was the primary cause of the delayed completion date on the City of Ventura Veterans Project. The analysis also found that no true concurrent contractor delays existed because the switchgear delay controlled the critical path.

NEWS

recent from Our Blog

Understanding the difference between schedulers and delay experts helps stakeholders choose the right support for construction projects.

Construction projects rely on accurate scheduling to keep work moving efficiently, but understanding why a project was delayed requires a different level of analysis. While schedulers and delay experts both work with construction timelines, their responsibilities and methods are not the same. A scheduler focuses on creating and managing project schedules, while a delay expert investigates […]

Accurate documentation, including schedules, reports, and correspondence, helps establish the facts behind construction delay claims.

Construction delays can create serious financial and scheduling challenges, but the success of a delay claim often depends on the quality of documentation available. Without clear records, it can become difficult to prove when a delay occurred, who was responsible, and how the project was affected. A construction claims expert witness can help review schedules, correspondence, and […]