Olivewood Village

The Challenge

HPM Consultants was retained to evaluate delays affecting the Olivewood Apartments project and determine the causes of extended project completion. The dispute focused on delays related to window procurement and installation, elevator procurement, framing activities, smoke curtain installations, and deficiencies in project scheduling and management practices.

Our Services

HPM Consultants conducted a detailed forensic schedule and project management analysis to evaluate the impact of procurement delays, scheduling deficiencies, subcontractor coordination issues, and critical-path activities on project completion. The review included analysis of delay notices, schedule updates, procurement records, RFIs, subcontractor buyout activities, elevator systems, smoke curtain installations, and contemporaneous project correspondence.

Outcome

HPM Consultants determined that the project experienced substantial delays, primarily due to poor project management, procurement failures, delayed subcontractor coordination, and unrealistic schedule assumptions. The analysis concluded that key activities, including smoke curtain procurement and elevator-related work, became critical gating items that significantly impacted inspections, Certificate of Occupancy milestones, and overall project completion. HPM Consultants subsequently presented these findings and provided expert testimony at arbitration, offering a clear and authoritative account of the delay causation and its impact on the project timeline.

NEWS

recent from Our Blog

5 Critical Questions Every Project Manager Should Ask A construction schedule is more than a project management tool. When delays, disruptions, or disputes arise, it can become a critical piece of evidence in determining what happened, why it happened, and who may be responsible. A schedule that looks complete on paper may still contain weaknesses […]

Every strong claim starts with a decision made long before trial, contact HPM Consultants

Every strong delay claim has a paper trail of decisions behind it. Those decisions get made months, sometimes years, before anyone sets foot in a courtroom. A careful construction delay analysis starts long before trial, not during it. Understanding what actually makes a claim defensible helps owners and contractors make smarter choices from day one. This […]