Explore how HPM Consultants brings clarity to complex scheduling,delay and damages disputes.
HPM Consultants was retained to evaluate schedule delays on the San Francisco Flower Market project and determine the actual causes affecting substantial completion. The assignment focused on analyzing contractor delay claims, critical path activities, and whether alleged delays materially impacted project completion.


HPM Consultants performed a forensic window analysis and schedule review to evaluate delay events across multiple project phases. The assessment examined structural work, MEP rough-ins, power installation, permits, procurement activities, and site improvements to determine their effect on project completion.
While the contractor claimed 246 days of delay and over $5.4 million in compensable damages, HPM Consultants’ analysis determined only 36 non-compensable delay days with no compensable entitlement. The findings established the actual schedule drivers and supported a fact-based assessment of completion delays and liquidated damages exposure.


5 Critical Questions Every Project Manager Should Ask A construction schedule is more than a project management tool. When delays, disruptions, or disputes arise, it can become a critical piece of evidence in determining what happened, why it happened, and who may be responsible. A schedule that looks complete on paper may still contain weaknesses […]

Every strong delay claim has a paper trail of decisions behind it. Those decisions get made months, sometimes years, before anyone sets foot in a courtroom. A careful construction delay analysis starts long before trial, not during it. Understanding what actually makes a claim defensible helps owners and contractors make smarter choices from day one. This […]