Case Studies

Explore how HPM Consultants brings clarity to complex scheduling,delay and damages disputes.

Valley Township Muncipal Building

The Challenge

HPM Consultants was retained by the contractor of a municipal building to evaluate alleged project delays associated with construction activities. The analysis focused on determining whether soil remediation delayed project completion or whether other contractor-related events were responsible for the extended completion date.

The project involved multiple concurrent construction and tenant-improvement activities that experienced numerous schedule revisions, redesigns, and added work scopes. Soil remediation impacted completion, prompting an independent forensic schedule review by HPM Consultants.

Our Services

HPM Consultants conducted a forensic schedule analysis and comprehensive review of project documents, schedules, and weekly status reports. The evaluation examined critical-path impacts, delay-event timing, contractor coordination issues, and the effect of project modifications on overall completion.

The investigation identified significant delays related to staircase redesigns, MEP modifications, PEMB wall panel revisions, and tenant-improvement changes. HPM Consultants also performed a but-for critical path analysis to determine whether the project completion date would have changed without the soil remediation activities.

Outcome

HPM Consultants conducted a comprehensive forensic schedule analysis and but-for critical path evaluation to determine the true drivers of project delay. The but-for analysis demonstrated that removal of the disputed event from the schedule did not alter the project completion date, establishing that other project events controlled the critical path throughout the relevant period. The findings provided a clear, fact-based conclusion supported by contemporaneous project records and accepted forensic scheduling methodologies, offering the client and counsel a defensible evidentiary foundation for the dispute resolution process.

NEWS

recent from Our Blog

Understanding the difference between schedulers and delay experts helps stakeholders choose the right support for construction projects.

Construction projects rely on accurate scheduling to keep work moving efficiently, but understanding why a project was delayed requires a different level of analysis. While schedulers and delay experts both work with construction timelines, their responsibilities and methods are not the same. A scheduler focuses on creating and managing project schedules, while a delay expert investigates […]

Accurate documentation, including schedules, reports, and correspondence, helps establish the facts behind construction delay claims.

Construction delays can create serious financial and scheduling challenges, but the success of a delay claim often depends on the quality of documentation available. Without clear records, it can become difficult to prove when a delay occurred, who was responsible, and how the project was affected. A construction claims expert witness can help review schedules, correspondence, and […]